Bathroom renovation – schedule of works

Nyblad Construction - bathroom renovation - sunshine coast

Bathroom renovation by Nyblad Construction

Every renovation is different. Tiles are different, layouts are different, electrical and plumbing are different. But in all these differences, we’ve come up with a schedule that is pretty much the same every time. So if you’re about to have your home invaded by tradies and you’re feeling a bit overwhelmed by the process, here’s a schedule of how we run things (99% of the time anyway!).

  1. Existing bathroom removed by Nyblad Construction, including uninstalling of shower mixers and any electrical modifications
  2. Installation of villaboard and plasterboard
  3. Installation of waterproofing
  4. Installation of tiles
  5. Installation of cabinetry
  6. Measure of shower screen and mirrors
  7. Installation of plumbing, fit off, reconnection and testing
  8. Electrical fit off, reconnection and testing
  9. Installation of accessories
  10. Painting
  11. Installation of shower screen and mirrors

You may find that on some days you will have multiple trades in your home and the next there may be none. Don’t be alarmed! It probably means we’re allowing time for things to set, dry, be delivered etc, and we’ve accounted for this in our timeline. Your renovation will be completed as per your contract. And if something should go very wrong and we’re delayed, we’ll let you know straight away.